Warehouse reinstatement is the work of returning a leased unit to the condition the lease requires, before the landlord inspects it. Offix reinstated a 5,000 sq ft warehouse in Singapore for SICK Product Center Asia — dismantling, demolition, making good and final cleaning — and handed it back in two weeks.
A commercial lease usually requires the tenant to return the unit in its original condition, less fair wear and tear. In practice that means every alteration made during the tenancy has to come out, and every surface it touched has to be made good — floors, walls, ceilings, and the electrical and lighting work added for the tenant’s operation.
For SICK Product Center Asia, the space was a 5,000 sq ft warehouse fitted out for its own use. The requirement was to strip that fit-out back, restore the base condition, and present the unit clean enough to pass a landlord inspection and close the tenancy.
The constraint was time. Reinstatement sits at the very end of a lease, so the deadline is fixed by the tenancy agreement rather than by the programme — the work has to finish before the lease expires, or the tenant carries the cost of holding over.
Warehouse reinstatement also differs from an office reinstatement in what has to come out. Industrial units carry heavier power supplies, larger openings and floor conditions that take more making-good than a partitioned office, so the restoration work is correspondingly heavier.

Only the works actually carried out on this project. This list is the deliverable a landlord and a surveyor check against at inspection.
There is no styled “after” in a reinstatement — the finished result is an empty unit. The proof is the same space at three points: as found with the tenant’s fit-out in place, during strip-out, and after making good and final cleaning.



Photograph the cleared space in daylight with the ceiling and floor both visible. That is the record a landlord’s surveyor works from, and it is the tenant’s evidence if the inspection is ever disputed.
Most reinstatement disputes are not about the large demolition items. They are about the details a surveyor checks at inspection: patches where a partition met the wall, ceiling tiles that do not match, floor finish that stops short of where equipment stood, lighting circuits left dead, and cable cut back but not removed.
Making good is what decides whether a unit passes first time. On this project the flooring, walls and ceilings were reinstated as a set rather than patched in isolation, the electrical and lighting works were returned to base condition, and the unit was cleaned before handover so the inspection was of the reinstatement itself and not of the debris around it.
Passing first time matters because a failed inspection costs days at the one point in a lease when there are none left. Where making-good crosses into genuine construction work it is sequenced like any renovation and construction package, not patched at the end.

square feet reinstated
weeks on site
scope packages delivered